Basin 4 Schedule
Dock Schedule
• Demolition - Sept 9, 2011 to Sept. 29, 2011
Completed

• Pile Removal – Sept. 27, 2011 to Sept. 30, 2011
Completed

• Dredging – Oct. 3, 2011 to Oct. 28, 2011
Completed November 8, 2011

• Pile Installation – Oct. 31, 2011 to Nov. 23, 2011
Started on November 9, 2011
• Float Installation – Nov. 7, 2011 to Feb. 13, 2012
Floats arrived 8, 2011
• Utilities Installation – Nov. 7, 2011 to Feb. 17, 2012
Restroom Schedule
• Demolition – Sept. 30, 2011 to Oct. 4, 2011
• Utilities – Oct. 5, 2011 to Oct. 18, 2011
• Foundation/Walls - Oct. 19, 2011 to Dec. 6, 2011
• Roof/Interior Finish - Dec. 7, 2011 to Jan. 17, 2012
• Sidewalk/Landscape – Jan. 18, 2012 to Jan. 31, 2012
Parking Lots
• Utilities Installation- Sept. 27, 2011 to Oct. 24, 2011
• Grinding – Oct. 25, 2011 to Nov. 7, 2011
• Paving and Striping – Dec. 13, 2011 to Dec. 26, 2011
• Concrete / Sidewalks – Oct. 25, 2011 to Nov. 17, 2011
• Seawall Repair – Nov. 22, 2011 to Jan. 30, 2012
Eelgrass Mitigation Site Schedule
• Restroom demolition – Oct. 5, 2011 to Oct. 11, 2011
• Drive Piles – Oct. 12, 2011 to Oct. 18, 2011
• Excavate – Oct. 19, 2011 to Nov. 15, 2011
• Install Rip Rap – Nov. 16, 2011 to Nov. 29, 2011
• Fencing/Sidewalk – Nov. 30, 2011 to Dec. 12, 2011
Paving/Striping – Dec. 13, 2011 to Dec. 16, 2011
|